Assessment Year | 2001 |
---|---|
Principal Product | Industrial Marking Systems |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
54,000
ft2
|
Annual Production | 18,844
lb
|
Production Hrs. Annual | 2,431
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,482 | 951,240 |
kWh
|
$0.12 |
Electricity Demand | $71,829 | 3,920 |
kW-mo/yr
|
$18.32 |
Natural Gas | $15,613 | 2,309 |
MMBtu
|
$6.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,121 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,652 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $4,516 | $690 |
$4,063
97,569
kWh
|
$453
-
kW-mo/yr
|
- | - | - | |
02 | 2.7144: Install spectral reflectors / delamp | $3,488 | $7,385 |
$2,515
60,358
kWh
|
$973
-
kW-mo/yr
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $65 | $132 |
$49
1,172
kWh
|
$16
-
kW-mo/yr
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $513 | $40 |
$513
12,306
kWh
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $518 | $675 |
$518
12,306
kWh
|
- | - | - | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $628 | $560 |
$452
10,841
kWh
|
$176
-
kW-mo/yr
|
- | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,353 | $20 |
$3,353
145,328
kWh
|
- | - | - | - | |
08 | 2.4157: Establish a predictive maintenance program | $1,545 | $400 |
$1,105
26,370
kWh
|
$440
-
kW-mo/yr
|
- | - | - | |
09 | 2.7135: Install occupancy sensors | $1,150 | $500 |
$830
19,924
kWh
|
$320
-
kW-mo/yr
|
- | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $848 | $120 |
$663
11,427
kWh
|
$185
-
kW-mo/yr
|
- | - | - | |
11 | 2.2515: Use optimum thickness insulation | $538 | $510 | - | - |
$538
-
MMBtu
|
- | - | |
12 | 2.2414: Use waste heat from hot flue gases to preheat | $379 | $2,075 | - | - |
$379
-
MMBtu
|
- | - | |
13 | 2.2437: Recover waste heat from equipment | $474 | $780 | - | - |
$474
-
MMBtu
|
- | - | |
14 | 2.2511: Insulate bare equipment | $261 | $128 | - | - |
$261
-
MMBtu
|
- | - | |
15 | 2.2511: Insulate bare equipment | $135 | $69 | - | - |
$135
-
MMBtu
|
- | - | |
16 | 3.5211: Reuse scrap glass as feed stock | $48 | - | - | - | - |
$48
-
lb
|
- | |
17 | 4.652: Replace existing equipment with more suitable substitutes | $1,662 | $1,500 | - |
$53
-
kW-mo/yr
|
- | - | $1,609 | |
18 | 4.652: Replace existing equipment with more suitable substitutes | $20,000 | $1,300 | - | - | - | - | $20,000 | |
TOTAL RECOMMENDED | $40,121 | $16,884 |
$14,061
397,601
kWh
|
$2,616
-
kW-mo/yr
|
$1,787
-
MMBtu
|
$48
-
lb
|
$21,609 | ||
TOTAL IMPLEMENTED | $10,652 | $3,692 |
$8,144
190,743
kWh
|
$1,574
-
kW-mo/yr
|
$934
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs