Assessment Year | 2000 |
---|---|
Principal Product | Cold drawn steel tubing |
NAICS |
n/a
|
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 47 |
Plant Area |
68,000
ft2
|
Annual Production | 700
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $135,474 | 2,762,016 |
kWh
|
$0.049 |
Electricity Demand | $54,103 | 6,279 |
kW-mo/yr
|
$8.62 |
Electricity Fees | $4,913 | - |
|
- |
Natural Gas | $94,686 | 28,083 |
MMBtu
|
$3.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $180,554 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,797 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $355 | $953 |
$147
4,982
kWh
|
$208
-
kW-mo/yr
|
- | - | - | |
02 | 2.4157: Establish a predictive maintenance program | $3,005 | $577 |
$1,979
67,116
kWh
|
$1,026
-
kW-mo/yr
|
- | - | - | |
03 | 2.2113: Repair or replace steam traps | $735 | $1,030 | - | - |
$735
-
MMBtu
|
- | - | |
04 | 2.2511: Insulate bare equipment | $1,914 | $535 | - | - |
$1,914
-
MMBtu
|
- | - | |
05 | 2.2514: Cover open tanks | $3,228 | $1,336 | - | - |
$3,228
-
MMBtu
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $233 | $129 |
$233
7,913
kWh
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $223 | $45 |
$223
7,620
kWh
|
- | - | - | - | |
08 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $337 | $222 |
$337
29,308
kWh
|
- | - | - | - | |
09 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $18,899 | $3,577 |
$18,899
1,694,607
kWh
|
- | - | - | - | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $123,125 | $120,000 | - | - | - |
$123,125
-
gal
|
- | |
11 | 4.424: Improve space comfort conditioning | $6,500 | $8,000 | - | - | - | - | $6,500 | |
12 | 4.114: Add/modify equipment to improve drying process | $22,000 | $4,000 | - | - | - | - | $22,000 | |
TOTAL RECOMMENDED | $180,554 | $140,404 |
$21,818
1,811,546
kWh
|
$1,234
-
kW-mo/yr
|
$5,877
-
MMBtu
|
$123,125
-
gal
|
$28,500 | ||
TOTAL IMPLEMENTED | $9,797 | $4,698 |
$2,686
109,026
kWh
|
$1,234
-
kW-mo/yr
|
$5,877
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs