ITAC Assessment: OK0936
ITAC logo
ITAC Assessment: OK0936
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Bushels of grain
NAICS 493130: Farm Product Warehousing and Storage
SIC 5153: Grain and Field Beans
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 210,000
ft2
Annual Production 8,000,000
bushels
Production Hrs. Annual 4,992
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,631 2,962,800
kWh
Electricity Demand $321,603 17,271
kW-mo/yr
Electricity Fees $3,000 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,759

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $46,436 $29,439 - $46,436
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $27,106 $35,525 $27,106
695,032
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $323 $450 $323
8,276
kWh
-
04 2.7224: Reduce space conditioning during non-working hours $144 $316 $144
3,701
kWh
-
TOTAL RECOMMENDED $74,009 $65,730 $27,573
707,009
kWh
$46,436
TOTAL IMPLEMENTED $46,759 $29,889 $323
8,276
kWh
$46,436
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs