| Assessment Year | 2000 |
|---|---|
| Principal Product | Hardwood lumber and furniture |
| NAICS |
n/a
|
| SIC | 2426: Hardwood Dimension and Flooring Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 210 |
| Plant Area |
150,000
ft2
|
| Annual Production | 20,000,000
thousand feet
|
| Production Hrs. Annual | 5,125
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $696,459 | 11,403,869 |
kWh
|
$0.061 |
| Electricity Demand | $178,301 | 29,804 |
kW-mo/yr
|
$5.98 |
| Electricity Fees | $160,257 | - |
|
- |
| Natural Gas | $87,758 | 17,028 |
MMBtu
|
$5.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $138,597 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,003 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $132 | $180 | - | - |
$132
-
MMBtu
|
- | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $5,907 | $3,980 | - | - |
$5,907
-
MMBtu
|
- | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,889 | $1,000 | - | - |
$3,889
-
MMBtu
|
- | - | |
| 04 | 2.4157: Establish a predictive maintenance program | $4,675 | $800 |
$2,179
56,565
kWh
|
$2,496
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $1,544 | $240 |
$1,322
34,291
kWh
|
$222
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $2,113 | $720 |
$2,113
54,807
kWh
|
- | - | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,718 | $60 |
$3,718
96,424
kWh
|
- | - | - | - | |
| 08 | 2.8114: Change rate schedules or other changes in utility service | $11,068 | $300 | - | - |
$11,068
-
MMBtu
|
- | - | |
| 09 | 2.2511: Insulate bare equipment | $922 | $278 | - | - |
$922
-
MMBtu
|
- | - | |
| 10 | 2.2628: Utilize a less expensive cooling method | $1,435 | $530 |
$1,435
37,222
kWh
|
- | - | - | - | |
| 11 | 2.2625: Chill water to the highest temperature possible | $1,887 | $40 |
$1,887
48,945
kWh
|
- | - | - | - | |
| 12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,057 | $500 |
$2,057
53,341
kWh
|
- | - | - | - | |
| 13 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $3,000 | $600 | - | - | - |
$3,000
-
lb
|
- | |
| 14 | 3.5316: Contract a wood pallet recycling company | $56,250 | $300 | - | - | - |
$56,250
-
lb
|
- | |
| 15 | 3.5316: Contract a wood pallet recycling company | $20,000 | $300 | - | - | - |
$20,000
-
lb
|
- | |
| 16 | 4.652: Replace existing equipment with more suitable substitutes | $20,000 | $3,000 | - | - | - | - | $20,000 | |
| TOTAL RECOMMENDED | $138,597 | $12,828 |
$14,711
381,595
kWh
|
$2,718
-
kW-mo/yr
|
$21,918
-
MMBtu
|
$79,250
-
lb
|
$20,000 | ||
| TOTAL IMPLEMENTED | $26,003 | $2,398 |
$11,163
289,566
kWh
|
$2,718
-
kW-mo/yr
|
$12,122
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs