| Assessment Year | 2000 |
|---|---|
| Principal Product | Corrugated Packaging Material |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 97 |
| Plant Area |
224,000
ft2
|
| Annual Production | 400,000
thousand feet
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,391 | 3,174,678 |
kWh
|
$0.029 |
| Electricity Demand | $60,260 | 8,838 |
kW-mo/yr
|
$6.82 |
| Electricity Fees | $110,265 | - |
|
- |
| Natural Gas | $178,594 | 29,812 |
MMBtu
|
$5.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,789 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,455 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4314: Use synthetic lubricant | $1,154 | $560 |
$1,154
18,171
kWh
|
- | - | - | - | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $10,865 | $4,220 | - |
$10,865
-
MMBtu
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $3,752 | $169 | - |
$3,752
-
MMBtu
|
- | - | - | |
| 04 | 2.4157: Establish a predictive maintenance program | $1,768 | $800 |
$1,768
23,740
kWh
|
- | - | - | - | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,552 | $500 | - |
$1,552
-
MMBtu
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $782 | $416 |
$782
12,309
kWh
|
- | - | - | - | |
| 07 | 2.8114: Change rate schedules or other changes in utility service | $22,060 | - | - | - | - | $22,060 | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,141 | $23 |
$2,141
33,705
kWh
|
- | - | - | - | |
| 09 | 3.4154: Eliminate leaks in water lines and valves | $15,135 | $20,000 | - | - |
$15,135
-
Tgal
|
- | - | |
| 10 | 4.521: Clear and rent existing space | $6,000 | $100 | - | - | - | $6,000 | - | |
| 11 | 4.126: Install sensors to detect defects | $8,580 | $125 | - | - | - | - | $8,580 | |
| TOTAL RECOMMENDED | $73,789 | $26,913 |
$5,845
87,925
kWh
|
$16,169
-
MMBtu
|
$15,135
-
Tgal
|
$28,060 | $8,580 | ||
| TOTAL IMPLEMENTED | $39,455 | $1,677 |
$5,063
75,616
kWh
|
$3,752
-
MMBtu
|
- | $22,060 | $8,580 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs