Assessment Year | 1999 |
---|---|
Principal Product | Styrofoam products |
NAICS |
n/a
|
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
90,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $188,253 | 3,736,225 |
kWh
|
$0.050 |
Electricity Demand | $95,452 | 9,993 |
kW-mo/yr
|
$9.55 |
Natural Gas | $64,316 | 78,918 |
MMBtu
|
$0.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $273,163 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,321 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $5,581 | $7,800 | - | - |
$5,581
-
MMBtu
|
- | |
02 | 2.7144: Install spectral reflectors / delamp | $1,521 | $3,930 |
$796
15,826
kWh
|
$725
-
kW-mo/yr
|
- | - | |
03 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $73,012 | $62,000 |
$73,012
1,551,290
kWh
|
- | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $17,647 | $45,000 |
$10,807
214,830
kWh
|
$6,840
-
kW-mo/yr
|
- | - | |
05 | 3.6192: Use a less expensive method of waste removal | $10,800 | - | - | - | - | $10,800 | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,900 | $9,000 | - | - | - | $2,900 | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $43,030 | $54,952 | - | - | - | $43,030 | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $118,672 | $67,000 | - | - | - | $118,672 | |
TOTAL RECOMMENDED | $273,163 | $249,682 |
$84,615
1,781,946
kWh
|
$7,565
-
kW-mo/yr
|
$5,581
-
MMBtu
|
$175,402 | ||
TOTAL IMPLEMENTED | $12,321 | $3,930 |
$796
15,826
kWh
|
$725
-
kW-mo/yr
|
- | $10,800 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs