Assessment Year | 2000 |
---|---|
Principal Product | Speciality Chemicals |
NAICS |
n/a
|
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $1 M to 5M |
# of Employees | 180 |
Plant Area |
413,820
ft2
|
Annual Production | 0
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $287,086 | 12,949,297 |
kWh
|
$0.022 |
Electricity Demand | $136,954 | 19,158 |
kW-mo/yr
|
$7.15 |
Electricity Fees | $167,525 | - |
|
- |
Natural Gas | $1,085,421 | 311,556 |
MMBtu
|
$3.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $228,507 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $82,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2162: Reduce excess steam bleeding | $9,583 | $50,000 |
$9,583
292,790
kWh
|
- | - | - | |
02 | 2.2113: Repair or replace steam traps | $50,000 | $13,000 | - |
$50,000
-
MMBtu
|
- | - | |
03 | 2.7444: Close holes and openings in building such as broken windows | $2,279 | $2,450 | - |
$2,279
-
MMBtu
|
- | - | |
04 | 2.7145: Install skylights | $1,074 | $3,450 |
$1,074
32,825
kWh
|
- | - | - | |
05 | 2.2135: Repair and eliminate steam leaks | $13,112 | $550 | - |
$13,112
-
MMBtu
|
- | - | |
06 | 2.1213: Direct warmest air to combustion intake | $14,087 | $10,840 | - |
$14,087
-
MMBtu
|
- | - | |
07 | 2.1213: Direct warmest air to combustion intake | $34,536 | $10,840 | - |
$34,536
-
MMBtu
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $355 | $528 |
$355
10,844
kWh
|
- | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $336 | $100 |
$336
10,258
kWh
|
- | - | - | |
10 | 2.1233: Analyze flue gas for proper air/fuel ratio | $18,683 | $1,000 | - |
$18,683
-
MMBtu
|
- | - | |
11 | 2.2423: Install waste heat boiler to produce steam | $53,063 | $100,000 | - |
$53,063
-
MMBtu
|
- | - | |
12 | 3.4111: Use closed cycle process to minimize waste water production | $17,828 | $10,000 | - | - |
$17,828
-
Tgal
|
- | |
13 | 3.4111: Use closed cycle process to minimize waste water production | $1,587 | $3,000 | - | - |
$1,587
-
Tgal
|
- | |
14 | 4.122: Develop standard procedures to improve internal yields | $11,984 | $1,500 | - | - | - | $11,984 | |
TOTAL RECOMMENDED | $228,507 | $207,258 |
$11,348
346,717
kWh
|
$185,760
-
MMBtu
|
$19,415
-
Tgal
|
$11,984 | ||
TOTAL IMPLEMENTED | $82,150 | $15,078 |
$355
10,844
kWh
|
$81,795
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs