ITAC Assessment: WV0060
ITAC logo
ITAC Assessment: WV0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Vinyl Windows
NAICS
n/a
SIC 3083: Laminated Plastics Plate, Sheet, and Profile Shapes
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area 150,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,750 308,324
kWh
Natural Gas $14,044 1,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,898 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,898

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $472 - $472
12,309
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $561 $1,803 $561
14,654
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $61 $168 $61
1,465
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $2,804 $2,600 - $2,804
-
MMBtu
TOTAL RECOMMENDED $3,898 $4,571 $1,094
28,428
kWh
$2,804
-
MMBtu
TOTAL IMPLEMENTED $3,898 $4,571 $1,094
28,428
kWh
$2,804
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs