ITAC Assessment: WV0045
ITAC logo
ITAC Assessment: WV0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Lehrs
NAICS
n/a
SIC 3567: Industrial Process Furnaces and Ovens
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 40,000
ft2
Annual Production 50
pieces
Production Hrs. Annual 4,800
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,444 411,196
kWh
Natural Gas $34,541 5,021
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,271

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $530 $740 $530
9,086
kWh
-
02 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $2,284 $960 - $2,284
-
MMBtu
03 2.7243: Improve air circulation with destratification fans / other methods $4,030 $4,400 - $4,030
-
MMBtu
04 2.6231: Utilize controls to operate equipment only when needed $2,270 $960 - $2,270
-
MMBtu
05 2.4231: Reduce the pressure of compressed air to the minimum required $960 $18 $960
16,413
kWh
-
06 2.4314: Use synthetic lubricant $156 - $156
2,638
kWh
-
07 2.7261: Install timers and/or thermostats $1,511 $900 - $1,511
-
MMBtu
TOTAL RECOMMENDED $11,741 $7,978 $1,646
28,137
kWh
$10,095
-
MMBtu
TOTAL IMPLEMENTED $5,271 $2,618 $1,490
25,499
kWh
$3,781
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs