| Assessment Year | 1994 |
|---|---|
| Principal Product | Lehrs |
| NAICS |
n/a
|
| SIC | 3567: Industrial Process Furnaces and Ovens |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
40,000
ft2
|
| Annual Production | 50
pieces
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,444 | 411,196 |
kWh
|
$0.059 |
| Natural Gas | $34,541 | 5,021 |
MMBtu
|
$6.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,271 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $530 | $740 |
$530
9,086
kWh
|
- | |
| 02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,284 | $960 | - |
$2,284
-
MMBtu
|
|
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $4,030 | $4,400 | - |
$4,030
-
MMBtu
|
|
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $2,270 | $960 | - |
$2,270
-
MMBtu
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $960 | $18 |
$960
16,413
kWh
|
- | |
| 06 | 2.4314: Use synthetic lubricant | $156 | - |
$156
2,638
kWh
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $1,511 | $900 | - |
$1,511
-
MMBtu
|
|
| TOTAL RECOMMENDED | $11,741 | $7,978 |
$1,646
28,137
kWh
|
$10,095
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,271 | $2,618 |
$1,490
25,499
kWh
|
$3,781
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs