Assessment Year | 1992 |
---|---|
Principal Product | ZN,PHOSPHATE ELECTROPLATING |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $274,103 | 3,333,236 |
kWh
|
$0.082 |
Natural Gas | $149,472 | 111,948 |
MMBtu
|
$1.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,339 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $15,304 | $17,920 |
$15,304
189,039
kWh
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $11,245 | $5,000 | - |
$11,245
-
MMBtu
|
- | |
03 | 2.1213: Direct warmest air to combustion intake | $645 | $500 | - |
$645
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,741 | $749 |
$4,063
49,531
kWh
|
- | $(-322.0) | |
05 | 2.4221: Install compressor air intakes in coolest locations | $404 | $400 |
$404
4,982
kWh
|
- | - | |
06 | 2.7492: Use proper thickness of insulation on building envelope | $565 | $1,800 | - |
$565
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $31,904 | $26,369 |
$19,771
243,552
kWh
|
$12,455
-
MMBtu
|
$(-322.0) | ||
TOTAL IMPLEMENTED | $31,339 | $24,569 |
$19,771
243,552
kWh
|
$11,890
-
MMBtu
|
$(-322.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs