ITAC Assessment: WV0015
ITAC logo
ITAC Assessment: WV0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Sun Glasses
NAICS
n/a
SIC 3851: Ophthalmic Goods
Sales Range $10
M
to 50
M
# of Employees 800
Plant Area 121,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $597,287 14,180,833
kWh
Natural Gas $105,458 15,700
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,448 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,448

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,512 $1,967 $2,512
195,780
kWh
-
02 2.4133: Use most efficient type of electric motors $3,304 $46,430 $3,304
64,185
kWh
-
03 2.7444: Close holes and openings in building such as broken windows $1,335 $250 - $1,335
-
MMBtu
04 2.7447: Install vinyl strip / high speed / air curtain doors $6,175 $870 - $6,175
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $669 $244 $669
52,169
kWh
-
06 2.1213: Direct warmest air to combustion intake $8,836 $1,961 - $8,836
-
MMBtu
07 2.2614: Use cooling tower or economizer to replace chiller cooling $1,579 $1,400 $1,579
123,095
kWh
-
08 2.2511: Insulate bare equipment $272 $42 - $272
-
MMBtu
09 2.2511: Insulate bare equipment $766 $2,995 $555
24,326
kWh
$211
-
MMBtu
TOTAL RECOMMENDED $25,448 $56,159 $8,619
459,555
kWh
$16,829
-
MMBtu
TOTAL IMPLEMENTED $25,448 $56,159 $8,619
459,555
kWh
$16,829
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs