| Assessment Year | 1993 |
|---|---|
| Principal Product | Exterior Plastic Body Pa |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 273 |
| Plant Area |
439,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $640,431 | 14,735,639 |
kWh
|
$0.043 |
| Natural Gas | $296,584 | 71,226 |
MMBtu
|
$4.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $63,363 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,135 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $368 | $888 |
$368
16,999
kWh
|
- | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $153 | $194 | - |
$153
-
MMBtu
|
|
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $32,010 | $6,000 | - |
$32,010
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $1,850 | $1,173 | - |
$1,850
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $1,163 | $976 | - |
$1,163
-
MMBtu
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $425 | $295 |
$425
19,637
kWh
|
- | |
| 07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $27,394 | $1,440 | - |
$27,394
-
MMBtu
|
|
| TOTAL RECOMMENDED | $63,363 | $10,966 |
$793
36,636
kWh
|
$62,570
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,135 | $2,905 |
$425
19,637
kWh
|
$28,710
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs