ITAC Assessment: WV0008
ITAC logo
ITAC Assessment: WV0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Signage in Bronze
NAICS
n/a
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $10
M
to 50
M
# of Employees 156
Plant Area 63,500
ft2
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $295,533 4,597,304
kWh
Natural Gas $50,268 9,989
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,039

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7243: Improve air circulation with destratification fans / other methods $1,872 $1,600 - $1,872
-
MMBtu
02 2.4221: Install compressor air intakes in coolest locations $966 $582 $966
35,756
kWh
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $1,773 $598 - $1,773
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $419 $576 $419
15,533
kWh
-
05 2.4133: Use most efficient type of electric motors $100 $7,275 $100
3,810
kWh
-
06 2.6212: Turn off equipment during breaks, reduce operating time $285 - - $285
-
MMBtu
07 2.2443: Re-use or recycle hot or cold process exhaust air $12,781 $408 - $12,781
-
MMBtu
08 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa $2,138 $2,057 $2,138
79,132
kWh
-
09 2.2437: Recover waste heat from equipment $1,407 $682 - $1,407
-
MMBtu
TOTAL RECOMMENDED $21,741 $13,778 $3,623
134,231
kWh
$18,118
-
MMBtu
TOTAL IMPLEMENTED $16,039 $9,439 $1,485
55,099
kWh
$14,554
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs