| Assessment Year | 1993 |
|---|---|
| Principal Product | Signage in Bronze |
| NAICS |
n/a
|
| SIC | 3369: Nonferrous Foundries, Except Aluminum and Copper |
| Sales Range | $10 M to 50M |
| # of Employees | 156 |
| Plant Area |
63,500
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $295,533 | 4,597,304 |
kWh
|
$0.064 |
| Natural Gas | $50,268 | 9,989 |
MMBtu
|
$5.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,039 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $1,872 | $1,600 | - |
$1,872
-
MMBtu
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $966 | $582 |
$966
35,756
kWh
|
- | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,773 | $598 | - |
$1,773
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $419 | $576 |
$419
15,533
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $100 | $7,275 |
$100
3,810
kWh
|
- | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $285 | - | - |
$285
-
MMBtu
|
|
| 07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $12,781 | $408 | - |
$12,781
-
MMBtu
|
|
| 08 | 2.2525: Eliminate cooling of process streams which subsequently must be heated and vice versa | $2,138 | $2,057 |
$2,138
79,132
kWh
|
- | |
| 09 | 2.2437: Recover waste heat from equipment | $1,407 | $682 | - |
$1,407
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,741 | $13,778 |
$3,623
134,231
kWh
|
$18,118
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $16,039 | $9,439 |
$1,485
55,099
kWh
|
$14,554
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs