Assessment Year | 1993 |
---|---|
Principal Product | Mining Equipments |
NAICS |
n/a
|
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
87,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,820 | 1,511,137 |
kWh
|
$0.071 |
Fuel Oil #6 | $28,659 | 5,331 |
MMBtu
|
$5.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,433 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,925 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,508 | $1,357 |
$4,508
132,474
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $1,068 | $5,630 |
$1,068
27,550
kWh
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $473 | $290 | - |
$473
-
MMBtu
|
|
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $300 | $86 | - |
$300
-
MMBtu
|
|
05 | 2.7243: Improve air circulation with destratification fans / other methods | $3,572 | $5,700 | - |
$3,572
-
MMBtu
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $25 | $35 |
$25
586
kWh
|
- | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $5,837 | $690 | - |
$5,837
-
MMBtu
|
|
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $650 | - |
$539
13,775
kWh
|
$111
-
MMBtu
|
|
TOTAL RECOMMENDED | $16,433 | $13,788 |
$6,140
174,385
kWh
|
$10,293
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,925 | $12,431 |
$1,632
41,911
kWh
|
$10,293
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs