ITAC Assessment: WM0198
ITAC logo
ITAC Assessment: WM0198
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Transportation Refrigeration Units, and R&D
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 535,000
ft2
Annual Production 600,000
units
Production Hrs. Annual 4,420
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $389,753 6,335,048
kWh
Electricity Demand $192,225 16,762
kW-mo/yr
Electricity Fees $138,392 -
Natural Gas $287,218 34,429
MMBtu
Waste Disposal Costs
Water Usage $37,442 2,795
Tgal
Water Disposal $13,975 2,795
Tgal
TOTAL YEARLY COSTS $1,059,005
RECOMMENDED SAVINGS* $45,044 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
01 2.3212: Optimize plant power factor $19,115 $49,375 - $19,115
-
kW-mo/yr
- - -
02 3.4116: Meter recycled water (to reduce sewer charges) $9,760 $1,950 - - - - $9,760
-
Tgal
03 2.3132: Recharge batteries on during off-peak demand periods $8,477 $12,900 - - $8,477 - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,991 $4,800 $1,436
23,167
kWh
$555
-
kW-mo/yr
- - -
05 2.7229: Air condition only space necessary $1,770 - - - - $1,770
-
MMBtu
-
06 2.4239: Eliminate or reduce compressed air usage $1,580 - $1,139
18,374
kWh
$440
-
kW-mo/yr
- - -
07 2.7444: Close holes and openings in building such as broken windows $808 $680 - - - $808
-
MMBtu
-
08 2.4221: Install compressor air intakes in coolest locations $799 $2,886 $576
9,294
kWh
$222
-
kW-mo/yr
- - -
09 2.7135: Install occupancy sensors $744 $320 $537
8,656
kWh
$208
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $45,044 $72,911 $3,688
59,491
kWh
$20,540
-
kW-mo/yr
$8,477 $2,578
-
MMBtu
$9,760
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs