ITAC Assessment: WM0124
ITAC logo
ITAC Assessment: WM0124
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Plastic Automotive Components, Aerospace, Metal Bellows Assemblies and E
NAICS 334419: Other Electronic Component Manufacturing
SIC 3625: Relays and Industrial Controls
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 100,000
ft2
Annual Production 9,346,010
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,582 1,779,863
kWh
Electricity Demand $35,831 5,071
kW-mo/yr
Electricity Fees $26,033 -
Natural Gas $12,238 2,355
MMBtu
Waste Disposal Costs
Water Usage $3,360 4,451
Tgal
TOTAL YEARLY COSTS $198,044
RECOMMENDED SAVINGS* $28,530 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,978

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $16,040 $13,392 $12,359
182,400
kWh
$3,681
-
kW-mo/yr
- - - -
02 2.8123: Pay utility bills on time $2,620 - - - $2,620 - - -
03 2.7221: Lower temperature during the winter season and vice-versa $1,534 - - - - $1,534
-
MMBtu
- -
04 2.7447: Install vinyl strip / high speed / air curtain doors $1,472 $690 - - - $1,472
-
MMBtu
- -
05 3.4116: Meter recycled water (to reduce sewer charges) $1,404 $405 - - - - $1,404
-
Tgal
-
06 2.4314: Use synthetic lubricant $1,387 $1,710 $1,210
17,913
kWh
$177
-
kW-mo/yr
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,363 $700 $1,193
17,610
kWh
$170
-
kW-mo/yr
- - - -
08 2.4221: Install compressor air intakes in coolest locations $1,192 $2,370 $1,043
15,401
kWh
$149
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $462 $630 $299
4,415
kWh
$42
-
kW-mo/yr
- - - $121
10 2.7447: Install vinyl strip / high speed / air curtain doors $291 $740 - - - $291
-
MMBtu
- -
11 2.7231: Use radiant heater for spot heating $248 $834 - - - $248
-
MMBtu
- -
12 2.7134: Use photocell controls $243 $340 $243
3,583
kWh
- - - - -
13 2.7111: Reduce illumination to minimum necessary levels $137 - $137
2,016
kWh
- - - - -
14 2.4111: Utilize energy-efficient belts and other improved mechanisms $80 $340 $59
875
kWh
$21
-
kW-mo/yr
- - - -
15 2.6218: Turn off equipment when not in use $57 - $57
839
kWh
- - - - -
TOTAL RECOMMENDED $28,530 $22,151 $16,600
245,052
kWh
$4,240
-
kW-mo/yr
$2,620 $3,545
-
MMBtu
$1,404
-
Tgal
$121
TOTAL IMPLEMENTED $2,978 $1,710 $1,267
18,752
kWh
$177
-
kW-mo/yr
- $1,534
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs