Assessment Year | 2018 |
---|---|
Principal Product | Plastic Automotive Components, Aerospace, Metal Bellows Assemblies and E |
NAICS | 334419: Other Electronic Component Manufacturing |
SIC | 3625: Relays and Industrial Controls |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
100,000
ft2
|
Annual Production | 9,346,010
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $120,582 | 1,779,863 |
kWh
|
$0.068 | |
Electricity Demand | $35,831 | 5,071 |
kW-mo/yr
|
$7.07 | |
Electricity Fees | $26,033 | - |
|
- | |
Natural Gas | $12,238 | 2,355 |
MMBtu
|
$5.20 | |
Waste Disposal Costs | |||||
Water Usage | $3,360 | 4,451 |
Tgal
|
$0.75 | |
TOTAL YEARLY COSTS | $198,044 | ||||
RECOMMENDED SAVINGS* | $28,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $2,978 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,040 | $13,392 |
$12,359
182,400
kWh
|
$3,681
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.8123: Pay utility bills on time | $2,620 | - | - | - | $2,620 | - | - | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $1,534 | - | - | - | - |
$1,534
-
MMBtu
|
- | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,472 | $690 | - | - | - |
$1,472
-
MMBtu
|
- | - | |
05 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,404 | $405 | - | - | - | - |
$1,404
-
Tgal
|
- | |
06 | 2.4314: Use synthetic lubricant | $1,387 | $1,710 |
$1,210
17,913
kWh
|
$177
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,363 | $700 |
$1,193
17,610
kWh
|
$170
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,192 | $2,370 |
$1,043
15,401
kWh
|
$149
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $462 | $630 |
$299
4,415
kWh
|
$42
-
kW-mo/yr
|
- | - | - | $121 | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $291 | $740 | - | - | - |
$291
-
MMBtu
|
- | - | |
11 | 2.7231: Use radiant heater for spot heating | $248 | $834 | - | - | - |
$248
-
MMBtu
|
- | - | |
12 | 2.7134: Use photocell controls | $243 | $340 |
$243
3,583
kWh
|
- | - | - | - | - | |
13 | 2.7111: Reduce illumination to minimum necessary levels | $137 | - |
$137
2,016
kWh
|
- | - | - | - | - | |
14 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $80 | $340 |
$59
875
kWh
|
$21
-
kW-mo/yr
|
- | - | - | - | |
15 | 2.6218: Turn off equipment when not in use | $57 | - |
$57
839
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $28,530 | $22,151 |
$16,600
245,052
kWh
|
$4,240
-
kW-mo/yr
|
$2,620 |
$3,545
-
MMBtu
|
$1,404
-
Tgal
|
$121 | ||
TOTAL IMPLEMENTED | $2,978 | $1,710 |
$1,267
18,752
kWh
|
$177
-
kW-mo/yr
|
- |
$1,534
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs