| Assessment Year | 2017 |
|---|---|
| Principal Product | Italian Cheese |
| NAICS | 311513: Cheese Manufacturing |
| SIC | 2022: Natural, Processed, and Imitation Cheese |
| Sales Range | $50 M to 100M |
| # of Employees | 140 |
| Plant Area |
90,000
ft2
|
| Annual Production | 87,000,000
lb
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,321,021 | 21,871,229 |
kWh
|
$0.060 |
| Electricity Demand | $491,531 | 36,359 |
kW-mo/yr
|
$13.52 |
| Electricity Fees | $89,764 | - |
|
- |
| Natural Gas | $762,074 | 271,600 |
MMBtu
|
$2.81 |
| TOTAL YEARLY COSTS | $2,664,390 | |||
| RECOMMENDED SAVINGS* | $194,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3112: Store heated/ cooled water for use during peak demand periods | $149,714 | $205,925 | - |
$106,746
-
kW-mo/yr
|
$42,968 | - | |
| 02 | 2.3137: Use power during off-peak periods | $23,950 | $64,500 | - |
$18,170
-
kW-mo/yr
|
$5,780 | - | |
| 03 | 2.2135: Repair and eliminate steam leaks | $9,764 | $1,490 |
$7,521
118,483
kWh
|
$2,243
-
kW-mo/yr
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $4,200 | $1,100 |
$3,240
51,035
kWh
|
$960
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,059 | $5,282 |
$3,126
49,249
kWh
|
$933
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $2,034 | $4,700 | - | - | - |
$2,034
-
MMBtu
|
|
| 07 | 2.2511: Insulate bare equipment | $1,239 | $863 | - | - | - |
$1,239
-
MMBtu
|
|
| TOTAL RECOMMENDED | $194,960 | $283,860 |
$13,887
218,767
kWh
|
$129,052
-
kW-mo/yr
|
$48,748 |
$3,273
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs