Assessment Year | 2015 |
---|---|
Principal Product | Transmissions |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
300,000
ft2
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $600,603 | 9,691,916 |
kWh
|
$0.062 |
Electricity Demand | $359,538 | 26,595 |
kW-mo/yr
|
$13.52 |
Natural Gas | $388,395 | 47,537 |
MMBtu
|
$8.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $178,744 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $51,767 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4145: Use magnetic technology to treat water | $7,657 | $15,000 | - | - | - |
$7,657
-
MMBtu
|
- | |
02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $44,425 | $42,690 | - | - | - |
$44,425
-
MMBtu
|
- | |
03 | 2.8112: Combine utility meters | $35,185 | $4,450 | - | - | $35,185 | - | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $25,416 | - | - | - | - |
$25,416
-
MMBtu
|
- | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $12,203 | $7,680 | - | - | - |
$12,203
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $7,737 | $654 | - | - | - |
$7,737
-
MMBtu
|
- | |
07 | 2.2437: Recover waste heat from equipment | $9,191 | $1,600 | - | - | - |
$9,191
-
MMBtu
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,586 | $1,680 |
$6,015
97,010
kWh
|
$2,571
-
kW-mo/yr
|
- | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $4,111 | $1,245 |
$2,883
46,500
kWh
|
$1,228
-
kW-mo/yr
|
- | - | - | |
10 | 2.7111: Reduce illumination to minimum necessary levels | $7,592 | $640 |
$5,626
90,740
kWh
|
$1,966
-
kW-mo/yr
|
- | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,495 | $10,871 |
$3,519
56,757
kWh
|
- | - | - | $2,976 | |
12 | 3.5316: Contract a wood pallet recycling company | $5,737 | - | - | - | - | - | $5,737 | |
13 | 2.3132: Recharge batteries on during off-peak demand periods | $3,678 | - | - | - | $3,678 | - | - | |
14 | 2.7135: Install occupancy sensors | $731 | $1,876 |
$518
8,356
kWh
|
$213
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $178,744 | $88,386 |
$18,561
299,363
kWh
|
$5,978
-
kW-mo/yr
|
$38,863 |
$106,629
-
MMBtu
|
$8,713 | ||
TOTAL IMPLEMENTED | $51,767 | $13,191 |
$15,160
244,507
kWh
|
$4,537
-
kW-mo/yr
|
$3,678 |
$25,416
-
MMBtu
|
$2,976 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs