ITAC Assessment: WI0516
ITAC logo
ITAC Assessment: WI0516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Precision machining
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 155
Plant Area 95,000
ft2
Annual Production 107,000,000
lb
Production Hrs. Annual 8,590
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,513 4,827,485
kWh
Electricity Demand $102,654 10,719
kW-mo/yr
Natural Gas $35,255 3,337
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,022,801 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,928

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Increase in Production Savings
01 4.132: Purchase new equipment to reduce material use / cost $987,800 - - - - $987,800
02 2.7142: Utilize higher efficiency lamps and/or ballasts $17,265 $33,480 $11,631
401,067
kWh
$5,634
-
kW-mo/yr
- -
03 2.7243: Improve air circulation with destratification fans / other methods $7,330 $1,600 - - $7,330
-
MMBtu
-
04 2.2437: Recover waste heat from equipment $5,311 $1,000 - - $5,311
-
MMBtu
-
05 2.4239: Eliminate or reduce compressed air usage $2,187 $325 $2,187
75,413
kWh
- - -
06 2.7261: Install timers and/or thermostats $1,556 $200 - - $1,556
-
MMBtu
-
07 2.4221: Install compressor air intakes in coolest locations $1,352 $2,560 $688
23,716
kWh
$664
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,022,801 $39,165 $14,506
500,196
kWh
$6,298
-
kW-mo/yr
$14,197
-
MMBtu
$987,800
TOTAL IMPLEMENTED $23,928 $37,040 $12,319
424,783
kWh
$6,298
-
kW-mo/yr
$5,311
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs