Assessment Year | 2006 |
---|---|
Principal Product | polymer products |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
Sales Range | $10 M to 50M |
# of Employees | 275 |
Plant Area |
75,000
ft2
|
Annual Production | 250,000,000
pieces
|
Production Hrs. Annual | 8,616
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $226,259 | 6,437,500 |
kWh
|
$0.035 |
Electricity Demand | $147,278 | 13,386 |
kW-mo/yr
|
$11.00 |
Natural Gas | $33,871 | 3,386 |
MMBtu
|
$10.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,916 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,647 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.424: Improve space comfort conditioning | $42,840 | $1,800 | - | - | - | $42,840 | |
02 | 4.424: Improve space comfort conditioning | $16,286 | $2,450 | - | - | - | $16,286 | |
03 | 2.2437: Recover waste heat from equipment | $10,175 | $1,000 | - | - |
$10,175
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,710 | $5,940 |
$2,584
69,660
kWh
|
$1,126
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $2,821 | $640 |
$1,901
51,234
kWh
|
$920
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,987 | $450 |
$1,987
53,558
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,529 | - |
$1,192
32,138
kWh
|
$337
-
kW-mo/yr
|
- | - | |
08 | 2.7261: Install timers and/or thermostats | $1,291 | $400 | - | - |
$1,291
-
MMBtu
|
- | |
09 | 2.3132: Recharge batteries on during off-peak demand periods | $1,277 | $200 | - |
$1,277
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $81,916 | $12,880 |
$7,664
206,590
kWh
|
$3,660
-
kW-mo/yr
|
$11,466
-
MMBtu
|
$59,126 | ||
TOTAL IMPLEMENTED | $50,647 | $8,340 |
$3,776
101,798
kWh
|
$2,740
-
kW-mo/yr
|
$1,291
-
MMBtu
|
$42,840 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs