ITAC Assessment: IA0015
ITAC logo
ITAC Assessment: IA0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product WASHING MACHINE TRANSMISSIONS
NAICS
n/a
SIC 3633: Household Laundry Equipment
Sales Range $10
M
to 50
M
# of Employees 203
Plant Area
n/a
Annual Production 934,000
pieces
Production Hrs. Annual 7,072
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $314,066 4,892,439
kWh
Natural Gas $25,093 8,599
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,292 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,292

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,595 - $4,987
77,667
kWh
- $(-392.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $846 $1,980 $846
13,189
kWh
- -
03 2.6232: Install set-back timers $440 $200 $440
6,741
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $4,364 $8,000 $4,364
67,995
kWh
- -
05 2.2437: Recover waste heat from equipment $3,896 $5,370 $(-489.0)
(-7,620)
kWh
$4,385
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $1,851 $100 $1,851
28,722
kWh
- -
07 2.4133: Use most efficient type of electric motors $3,300 $4,278 $3,300
51,290
kWh
- -
TOTAL RECOMMENDED $19,292 $19,928 $15,299
237,984
kWh
$4,385
-
MMBtu
$(-392.0)
TOTAL IMPLEMENTED $19,292 $19,928 $15,299
237,984
kWh
$4,385
-
MMBtu
$(-392.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs