Assessment Year | 2005 |
---|---|
Principal Product | Hoses & Tubes Assemblies |
NAICS | 332710: Machine Shops |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
90,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 6,400
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $79,001 | 2,137,600 |
kWh
|
$0.037 |
Electricity Demand | $54,216 | 5,300 |
kW-mo/yr
|
$10.23 |
Electricity Fees | $10,519 | - |
|
- |
Natural Gas | $46,541 | 4,972 |
MMBtu
|
$9.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,862 | $27,000 |
$9,126
235,200
kWh
|
$4,736
-
kW-mo/yr
|
- | - | |
02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,177 | $9,500 |
$1,277
32,918
kWh
|
$2,900
-
kW-mo/yr
|
- | - | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,880 | - | - | - | - | $3,880 | |
04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,880 | - | - | - | - | $3,880 | |
05 | 2.7261: Install timers and/or thermostats | $2,699 | - |
$1,526
39,340
kWh
|
$1,173
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,919 | - |
$1,852
47,744
kWh
|
$1,067
-
kW-mo/yr
|
- | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $2,670 | $520 |
$2,670
68,814
kWh
|
- | - | - | |
08 | 2.4312: Improve lubrication practices | $1,579 | $1,238 |
$1,040
26,796
kWh
|
$539
-
kW-mo/yr
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,524 | $1,280 |
$968
24,941
kWh
|
$556
-
kW-mo/yr
|
- | - | |
10 | 2.6121: Reduce hot water temperature to the minimum required | $1,374 | $1,500 | - | - |
$1,374
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $38,564 | $41,038 |
$18,459
475,753
kWh
|
$10,971
-
kW-mo/yr
|
$1,374
-
MMBtu
|
$7,760 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs