ITAC Assessment: WI0458
ITAC logo
ITAC Assessment: WI0458
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Industrial Cutting Tools
NAICS 332216: Saw Blade and Handtool Manufacturing
SIC 3427:
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 42,000
ft2
Annual Production 475,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,406 2,090,250
kWh
Electricity Demand $52,674 5,478
kW-mo/yr
Natural Gas $20,545 2,392
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,699 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,959

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,180 $17,325 $5,126
151,200
kWh
$3,054
-
kW-mo/yr
- - -
02 3.6192: Use a less expensive method of waste removal $6,420 $18,000 - - $(-7,305.0)
-
MMBtu
$13,725
-
gal
-
03 2.4112: Install soft-start to eliminate nuisance trips $4,400 $3,500 - $4,400
-
kW-mo/yr
- - -
04 2.7261: Install timers and/or thermostats $3,959 $7,900 - - $3,959
-
MMBtu
- -
05 3.7137: Replace cloth rags with paper towels $1,980 - - - - - $1,980
06 2.4224: Upgrade controls on compressors $1,707 $3,500 $1,707
50,335
kWh
- - - -
07 2.4221: Install compressor air intakes in coolest locations $1,053 $740 $728
21,480
kWh
$325
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $27,699 $50,965 $7,561
223,015
kWh
$7,779
-
kW-mo/yr
$(-3,346.0)
-
MMBtu
$13,725
-
gal
$1,980
TOTAL IMPLEMENTED $22,959 $46,725 $5,126
151,200
kWh
$7,454
-
kW-mo/yr
$(-3,346.0)
-
MMBtu
$13,725
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs