ITAC Assessment: WI0452
ITAC logo
ITAC Assessment: WI0452
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Sintered metal products
NAICS 332117: Powder Metallurgy Part Manufacturing
SIC 3399: Primary Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 75,000
ft2
Annual Production 5,200,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,545 7,108,800
kWh
Electricity Demand $126,026 13,448
kW-mo/yr
Electricity Fees $25,193 -
Natural Gas $104,829 15,233
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $123,806 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 3.4114: Replace city water with recycled water via cooling tower $54,337 $72,000 n/a $(-13,743.0)
(-268,560)
kWh
- - $68,080
-
Tgal
- -
02 3.6124: Burn waste oil for heat $44,636 $30,000 $(-1,326.0)
(-14,089)
kWh
- $23,962
-
MMBtu
- $22,000
-
gal
-
03 2.4224: Upgrade controls on compressors $5,692 $12,000 $5,692
181,278
kWh
- - - - -
04 2.7135: Install occupancy sensors $4,850 $2,700 $3,463
110,278
kWh
$1,387
-
kW-mo/yr
- - - -
05 3.7137: Replace cloth rags with paper towels $4,710 - - - - - - $4,710
06 2.7261: Install timers and/or thermostats $4,063 $1,000 - - $4,063
-
MMBtu
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,926 $8,580 $2,400
76,440
kWh
$1,526
-
kW-mo/yr
- - - -
08 2.2515: Use optimum thickness insulation $1,592 $687 $1,081
34,434
kWh
$511
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $123,806 $126,967 $(-2,433.0)
119,781
kWh
$3,424
-
kW-mo/yr
$28,025
-
MMBtu
$68,080
-
Tgal
$22,000
-
gal
$4,710
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs