| Assessment Year | 2003 |
|---|---|
| Principal Product | Laminating Products |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 62 |
| Plant Area |
240,000
ft2
|
| Annual Production | 10,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,488 | 2,796,133 |
kWh
|
$0.022 |
| Electricity Demand | $55,683 | 6,834 |
kW-mo/yr
|
$8.15 |
| Electricity Fees | $21,333 | - |
|
- |
| Natural Gas | $35,856 | 6,630 |
MMBtu
|
$5.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,094 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,197 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,587 | $13,005 |
$3,209
128,624
kWh
|
$2,378
-
kW-mo/yr
|
- | - | |
| 02 | 3.4111: Use closed cycle process to minimize waste water production | $3,564 | $4,300 | - | - | - |
$3,564
-
Tgal
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,434 | $1,918 |
$2,207
95,115
kWh
|
$1,227
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,870 | $5,000 |
$1,870
80,586
kWh
|
- | - | - | |
| 05 | 2.7261: Install timers and/or thermostats | $1,558 | $1,200 | - | - |
$1,558
-
MMBtu
|
- | |
| 06 | 2.1133: Adjust burners for efficient operation | $962 | $500 | - | - |
$962
-
MMBtu
|
- | |
| 07 | 2.7135: Install occupancy sensors | $610 | $300 |
$610
26,334
kWh
|
- | - | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $509 | $1,280 |
$315
13,564
kWh
|
$194
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $18,094 | $27,503 |
$8,211
344,223
kWh
|
$3,799
-
kW-mo/yr
|
$2,520
-
MMBtu
|
$3,564
-
Tgal
|
||
| TOTAL IMPLEMENTED | $6,197 | $13,305 |
$3,819
154,958
kWh
|
$2,378
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs