Assessment Year | 2003 |
---|---|
Principal Product | Injection Molded Plastic |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
37,500
ft2
|
Annual Production | 650,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,603 | 2,410,349 |
kWh
|
$0.036 |
Electricity Demand | $75,406 | 7,151 |
kW-mo/yr
|
$10.54 |
Electricity Fees | $14,303 | - |
|
- |
Natural Gas | $3,113 | 542 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,095 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $119 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,363 | $102,600 |
$28,363
748,406
kWh
|
- | - | - | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,768 | $200 | - | - | - |
$3,768
-
Tgal
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,276 | $1,424 | - | - |
$3,276
-
MMBtu
|
- | |
04 | 2.7261: Install timers and/or thermostats | $861 | $800 | - | - |
$861
-
MMBtu
|
- | |
05 | 2.7135: Install occupancy sensors | $496 | $225 |
$115
3,030
kWh
|
$381
-
kW-mo/yr
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $212 | $272 |
$118
3,108
kWh
|
$94
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $119 | $34 |
$67
2,370
kWh
|
$52
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $37,095 | $105,555 |
$28,663
756,914
kWh
|
$527
-
kW-mo/yr
|
$4,137
-
MMBtu
|
$3,768
-
Tgal
|
||
TOTAL IMPLEMENTED | $119 | $34 |
$67
2,370
kWh
|
$52
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs