Assessment Year | 2002 |
---|---|
Principal Product | Architectural Glass |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
44,000
ft2
|
Annual Production | 2,225
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $148,504 | 6,957,600 |
kWh
|
$0.021 |
Electricity Demand | $141,439 | 14,306 |
kW-mo/yr
|
$9.89 |
Electricity Fees | $55,568 | - |
|
- |
Natural Gas | $4,583 | 793 |
MMBtu
|
$5.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,431 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,615 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.1193: Convert from batch operation to continuous processing | $14,150 | $13,000 |
$(-1,200.0)
(-47,058)
kWh
|
- | - |
$18,600
-
Tgal
|
$(-3,250.0) | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,467 | $20,000 |
$9,467
420,744
kWh
|
- | - | - | - | |
03 | 2.3191: Use demand controller or load shedder | $4,530 | $1,000 |
$4,028
179,040
kWh
|
$8,402
-
kW-mo/yr
|
$(-7,900.0)
-
MMBtu
|
- | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,251 | $1,100 | - | - |
$2,251
-
MMBtu
|
- | - | |
05 | 2.7135: Install occupancy sensors | $1,228 | $4,000 |
$528
23,499
kWh
|
$700
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $519 | $740 |
$321
14,301
kWh
|
$198
-
kW-mo/yr
|
- | - | - | |
07 | 2.7224: Reduce space conditioning during non-working hours | $286 | $800 | - | - |
$286
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $32,431 | $40,640 |
$13,144
590,526
kWh
|
$9,300
-
kW-mo/yr
|
$(-5,363.0)
-
MMBtu
|
$18,600
-
Tgal
|
$(-3,250.0) | ||
TOTAL IMPLEMENTED | $27,615 | $38,840 |
$9,116
411,486
kWh
|
$898
-
kW-mo/yr
|
$2,251
-
MMBtu
|
$18,600
-
Tgal
|
$(-3,250.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs