Assessment Year | 2002 |
---|---|
Principal Product | Stainless Tubing |
NAICS |
n/a
|
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $50 M to 100M |
# of Employees | 190 |
Plant Area |
90,000
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $241,729 | 7,685,000 |
kWh
|
$0.031 |
Electricity Demand | $141,823 | 40,028 |
kW-mo/yr
|
$3.54 |
Electricity Fees | $22,719 | - |
|
- |
Natural Gas | $132,408 | 120,589 |
MMBtu
|
$1.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,410 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,343 | $1,400 |
$(-116.0)
(-3,497)
kWh
|
$9,459
-
MMBtu
|
|
02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,154 | $2,688 | - |
$7,154
-
MMBtu
|
|
03 | 2.7261: Install timers and/or thermostats | $4,470 | $600 | - |
$4,470
-
MMBtu
|
|
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,940 | $500 | - |
$2,940
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,752 | $8,000 | - |
$1,752
-
MMBtu
|
|
TOTAL RECOMMENDED | $25,659 | $13,188 |
$(-116.0)
(-3,497)
kWh
|
$25,775
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,410 | $1,100 | - |
$7,410
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs