| Assessment Year | 2002 |
|---|---|
| Principal Product | Stainless Tubing |
| NAICS |
n/a
|
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $50 M to 100M |
| # of Employees | 190 |
| Plant Area |
90,000
ft2
|
| Annual Production | 30,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $241,729 | 7,685,000 |
kWh
|
$0.031 |
| Electricity Demand | $141,823 | 40,028 |
kW-mo/yr
|
$3.54 |
| Electricity Fees | $22,719 | - |
|
- |
| Natural Gas | $132,408 | 120,589 |
MMBtu
|
$1.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,410 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,343 | $1,400 |
$(-116.0)
(-3,497)
kWh
|
$9,459
-
MMBtu
|
|
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,154 | $2,688 | - |
$7,154
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $4,470 | $600 | - |
$4,470
-
MMBtu
|
|
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,940 | $500 | - |
$2,940
-
MMBtu
|
|
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,752 | $8,000 | - |
$1,752
-
MMBtu
|
|
| TOTAL RECOMMENDED | $25,659 | $13,188 |
$(-116.0)
(-3,497)
kWh
|
$25,775
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,410 | $1,100 | - |
$7,410
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs