| Assessment Year | 2002 |
|---|---|
| Principal Product | Custom furniture |
| NAICS |
n/a
|
| SIC | 2517: Wood Television, Radio, Phonograph, and Sewing Machine Cabinets |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
100,000
ft2
|
| Annual Production | 13,000
pieces
|
| Production Hrs. Annual | 4,275
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $183,505 | 2,446,109 |
kWh
|
$0.075 |
| Electricity Demand | $79,883 | 8,069 |
kW-mo/yr
|
$9.90 |
| Electricity Fees | $17,982 | - |
|
- |
| Natural Gas | $91,237 | 10,824 |
MMBtu
|
$8.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,749 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $8,178 | $4,800 |
$(-241.0)
(-6,584)
kWh
|
- |
$8,419
-
MMBtu
|
|
| 02 | 2.7261: Install timers and/or thermostats | $5,395 | $600 | - | - |
$5,395
-
MMBtu
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,443 | - | - |
$5,443
-
kW-mo/yr
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,636 | $1,050 |
$(-16.0)
(-446)
kWh
|
- |
$4,652
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,885 | $20,800 |
$3,885
106,135
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,015 | $1,657 |
$1,876
51,278
kWh
|
$1,139
-
kW-mo/yr
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,255 | $7,140 |
$1,408
34,489
kWh
|
$847
-
kW-mo/yr
|
- | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $942 | $740 |
$589
16,095
kWh
|
$353
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $33,749 | $36,787 |
$7,501
200,967
kWh
|
$7,782
-
kW-mo/yr
|
$18,466
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,530 | $7,797 |
$2,224
60,789
kWh
|
$1,492
-
kW-mo/yr
|
$13,814
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs