| Assessment Year | 2001 |
|---|---|
| Principal Product | Finishing Operations |
| NAICS |
n/a
|
| SIC | 2675: Die-Cut Paper and Paperboard and Cardboard |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
61,895
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,151 | 1,500,642 |
kWh
|
$0.032 |
| Electricity Demand | $36,588 | 4,421 |
kW-mo/yr
|
$8.28 |
| Electricity Fees | $4,120 | - |
|
- |
| Natural Gas | $2,818 | 500 |
MMBtu
|
$5.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $117,238 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $814 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.445: Install equipment to move product | $104,000 | $4,000 | - | - | - | $104,000 | - | |
| 02 | 2.3191: Use demand controller or load shedder | $7,857 | $10,000 | - |
$7,857
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $1,503 | $1,500 |
$937
27,648
kWh
|
$566
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $838 | $3,744 |
$605
17,856
kWh
|
$233
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7135: Install occupancy sensors | $211 | $300 |
$211
6,210
kWh
|
- | - | - | - | |
| 06 | 3.7137: Replace cloth rags with paper towels | $1,277 | - | - | - | - | - | $1,277 | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $738 | $2,000 |
$409
12,058
kWh
|
$329
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $605 | $640 |
$436
12,872
kWh
|
$169
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.7261: Install timers and/or thermostats | $209 | $400 | - | - |
$209
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $117,238 | $22,584 |
$2,598
76,644
kWh
|
$9,154
-
kW-mo/yr
|
$209
-
MMBtu
|
$104,000 | $1,277 | ||
| TOTAL IMPLEMENTED | $814 | $1,040 |
$436
12,872
kWh
|
$169
-
kW-mo/yr
|
$209
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs