| Assessment Year | 2001 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 103 |
| Plant Area |
65,000
ft2
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $150,087 | 4,824,736 |
kWh
|
$0.031 |
| Electricity Demand | $160,014 | 18,144 |
kW-mo/yr
|
$8.82 |
| Electricity Fees | $15,854 | - |
|
- |
| Natural Gas | $24,316 | 5,114 |
MMBtu
|
$4.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $10,705 | $54,000 |
$4,856
148,593
kWh
|
$13,890
-
kW-mo/yr
|
$(-8,041.0)
-
MMBtu
|
- | |
| 02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,134 | - | - | - | - |
$2,134
-
lb
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,744 | $1,580 |
$1,065
32,532
kWh
|
$679
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,411 | $480 |
$849
26,084
kWh
|
$562
-
kW-mo/yr
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $1,265 | $1,000 | - | - |
$1,265
-
MMBtu
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $613 | $562 |
$379
11,723
kWh
|
$234
-
kW-mo/yr
|
- | - | |
| 07 | 2.7261: Install timers and/or thermostats | $336 | $200 | - | - |
$336
-
MMBtu
|
- | |
| 08 | 2.7144: Install spectral reflectors / delamp | $190 | - |
$123
3,810
kWh
|
$67
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $18,398 | $57,822 |
$7,272
222,742
kWh
|
$15,432
-
kW-mo/yr
|
$(-6,440.0)
-
MMBtu
|
$2,134
-
lb
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs