| Assessment Year | 1988 |
|---|---|
| Principal Product | RECREATIONAL KNIVES |
| NAICS |
n/a
|
| SIC | 3421: Cutlery |
| Sales Range | $1 M to 5M |
| # of Employees | 82 |
| Plant Area |
n/a
|
| Annual Production | 354,000
pieces
|
| Production Hrs. Annual | 3,250
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,676 | 1,505,862 |
kWh
|
$0.058 |
| Natural Gas | $16,230 | 4,001 |
MMBtu
|
$4.06 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,799 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $711 | $500 |
$711
12,309
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $683 | $375 |
$683
11,723
kWh
|
- | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $889 | - |
$889
15,533
kWh
|
- | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,270 | $10,400 |
$(-212.0)
(-3,810)
kWh
|
$4,482
-
MMBtu
|
|
| 05 | 2.7261: Install timers and/or thermostats | $2,794 | $4,000 | - |
$2,794
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $162 | $349 |
$162
2,931
kWh
|
- | |
| 07 | 2.3191: Use demand controller or load shedder | $4,867 | $3,600 |
$4,867
-
kWh
|
- | |
| 08 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $5,514 | $1,000 | - |
$5,514
-
MMBtu
|
|
| 09 | 2.1123: Install automatic stack damper | $677 | $900 | - |
$677
-
MMBtu
|
|
| 10 | 2.8121: Apply for tax-free status for energy purchases | $487 | $250 | - |
$487
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,054 | $21,374 |
$7,100
38,686
kWh
|
$13,954
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,799 | $5,074 |
$7,312
42,496
kWh
|
$487
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs