ITAC Assessment: WI0374
ITAC logo
ITAC Assessment: WI0374
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Paints, Primers, and Coatings
NAICS
n/a
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 136
Plant Area 131,430
ft2
Annual Production 32,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,732 2,811,841
kWh
Electricity Demand $82,584 6,768
kW-mo/yr
Electricity Fees $10,871 -
Natural Gas $54,505 17,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $428,633 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,045

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 4.132: Purchase new equipment to reduce material use / cost $322,000 $100,000 - - - - $34,000 $288,000
02 4.448: Install automatic part storage / retreval system $42,500 $75,000 - - - - $42,500 -
03 4.426: Modify workload $34,000 $2,000 - - - - $34,000 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $9,097 $26,587 $5,624
114,009
kWh
$3,473
-
kW-mo/yr
- - - -
05 2.7135: Install occupancy sensors $4,012 $12,000 $2,624
53,341
kWh
$1,388
-
kW-mo/yr
- - - -
06 2.3134: Shift from daytime to nighttime operation $8,307 - $8,307
157,386
kWh
- - - - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $2,711 $8,000 - - - $3,136
-
lb
$(-425.0) -
08 2.1233: Analyze flue gas for proper air/fuel ratio $2,394 $500 - - $2,394
-
MMBtu
- - -
09 2.4221: Install compressor air intakes in coolest locations $1,934 $940 $1,062
21,395
kWh
$872
-
kW-mo/yr
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $514 $120 $325
6,741
kWh
$189
-
kW-mo/yr
- - - -
11 3.6192: Use a less expensive method of waste removal $738 - - - - $738
-
lb
- -
12 2.7447: Install vinyl strip / high speed / air curtain doors $426 $2,040 $(-17.0)
(-293)
kWh
- $443
-
MMBtu
- - -
TOTAL RECOMMENDED $428,633 $227,187 $17,925
352,579
kWh
$5,922
-
kW-mo/yr
$2,837
-
MMBtu
$3,874
-
lb
$110,075 $288,000
TOTAL IMPLEMENTED $40,045 $12,660 $308
6,448
kWh
$189
-
kW-mo/yr
$2,837
-
MMBtu
$3,136
-
lb
$33,575 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs