ITAC Assessment: WI0372
ITAC logo
ITAC Assessment: WI0372
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Lithographic Printed Products
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 92
Plant Area 55,000
ft2
Annual Production 5,320,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,260 2,349,648
kWh
Electricity Demand $64,754 5,278
kW-mo/yr
Electricity Fees $12,386 -
Natural Gas $4,383 972
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $251,319 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.431: Train operators for maximum operating efficiency $201,600 - - - - - $201,600
02 4.611: Begin a practice of predictive / preventative maintenance $36,000 - - - - - $36,000
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,349 $13,911 $2,737
75,029
kWh
$1,612
-
kW-mo/yr
- - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,060 - - - - $4,060
-
lb
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,804 $2,000 $1,320
36,049
kWh
$1,484
-
kW-mo/yr
- - -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,632 - - $1,632
-
kW-mo/yr
- - -
07 2.4221: Install compressor air intakes in coolest locations $737 $640 $492
13,482
kWh
$245
-
kW-mo/yr
- - -
08 2.7261: Install timers and/or thermostats $137 $400 - - $137
-
MMBtu
- -
TOTAL RECOMMENDED $251,319 $16,951 $4,549
124,560
kWh
$4,973
-
kW-mo/yr
$137
-
MMBtu
$4,060
-
lb
$237,600
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs