ITAC Assessment: WI0367
ITAC logo
ITAC Assessment: WI0367
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Duplicator Presses
NAICS
n/a
SIC 3861: Photographic Equipment and Supplies
Sales Range $10
M
to 50
M
# of Employees 111
Plant Area 107,000
ft2
Annual Production 650
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,083 2,087,925
kWh
Electricity Demand $78,561 6,311
kW-mo/yr
Electricity Fees $12,919 -
Natural Gas $50,662 13,636
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $106,927 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.431: Train operators for maximum operating efficiency $57,375 - n/a - - - - $57,375 -
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $14,201 - n/a - - - $14,201
-
lb
- -
03 3.5315: Lease / purchase baler; sell cardboard to recycler $12,036 $9,000 n/a - - - $12,374
-
lb
$(-338.0) -
04 2.7261: Install timers and/or thermostats $7,036 $800 n/a - - $7,036
-
MMBtu
- - -
05 2.7221: Lower temperature during the winter season and vice-versa $4,226 - n/a - - $4,226
-
MMBtu
- - -
06 2.7243: Improve air circulation with destratification fans / other methods $3,882 $5,500 n/a $(-313.0)
(-8,792)
kWh
- $4,195
-
MMBtu
- - -
07 2.3134: Shift from daytime to nighttime operation $4,657 - n/a - $4,657
-
kW-mo/yr
- - - -
08 4.821: Pay bills on time to avoid late fees $2,436 - n/a - - - - - $2,436
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $928 $1,092 n/a $256
7,034
kWh
$672
-
kW-mo/yr
- - - -
10 2.4221: Install compressor air intakes in coolest locations $150 $640 n/a $39
1,172
kWh
$111
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $106,927 $17,032 $(-18.0)
(-586)
kWh
$5,440
-
kW-mo/yr
$15,457
-
MMBtu
$26,575
-
lb
$57,037 $2,436
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs