ITAC Assessment: WI0354
ITAC logo
ITAC Assessment: WI0354
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Direct Current Motors
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 47,000
ft2
Annual Production 4,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,888 741,501
kWh
Electricity Demand $32,075 2,576
kW-mo/yr
Electricity Fees $13,754 -
Natural Gas $26,761 5,239
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,099 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,323

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $7,740 $21,000 $2,453
55,979
kWh
$8,810
-
kW-mo/yr
$(-3,523.0)
-
MMBtu
- - - - -
02 2.8114: Change rate schedules or other changes in utility service $5,469 $500 - - $5,469
-
MMBtu
- - - - -
03 3.6192: Use a less expensive method of waste removal $5,465 - - - - - $5,465
-
lb
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,567 $18,988 $1,597
36,342
kWh
$1,970
-
kW-mo/yr
- - - - - -
05 3.2123: Convert to high volume low pressure (hvlp) paint guns $2,618 $500 - - - - - - - $2,618
06 2.7261: Install timers and/or thermostats $2,328 $400 - - $2,328
-
MMBtu
- - - - -
07 3.8142: Distill contaminated solvents for reuse $1,418 $4,850 - - - $1,749
-
gal
$(-87.0)
-
lb
$(-154.0) $(-90.0) -
08 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,284 $5,000 - - - - $1,284
-
lb
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $477 $180 $210
4,689
kWh
$267
-
kW-mo/yr
- - - - - -
10 2.4221: Install compressor air intakes in coolest locations $373 $640 $165
3,810
kWh
$208
-
kW-mo/yr
- - - - - -
11 2.2437: Recover waste heat from equipment $360 $800 - - $360
-
MMBtu
- - - - -
TOTAL RECOMMENDED $31,099 $52,858 $4,425
100,820
kWh
$11,255
-
kW-mo/yr
$4,634
-
MMBtu
$1,749
-
gal
$6,662
-
lb
$(-154.0) $(-90.0) $2,618
TOTAL IMPLEMENTED $19,323 $26,508 $1,972
44,841
kWh
$2,445
-
kW-mo/yr
$8,157
-
MMBtu
- $6,749
-
lb
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs