Assessment Year | 1999 |
---|---|
Principal Product | Direct Current Motors |
NAICS |
n/a
|
SIC | 3621: Motors and Generators |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
47,000
ft2
|
Annual Production | 4,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,888 | 741,501 |
kWh
|
$0.042 |
Electricity Demand | $32,075 | 2,576 |
kW-mo/yr
|
$12.45 |
Electricity Fees | $13,754 | - |
|
- |
Natural Gas | $26,761 | 5,239 |
MMBtu
|
$5.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,099 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,323 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $7,740 | $21,000 |
$2,453
55,979
kWh
|
$8,810
-
kW-mo/yr
|
$(-3,523.0)
-
MMBtu
|
- | - | - | - | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $5,469 | $500 | - | - |
$5,469
-
MMBtu
|
- | - | - | - | - | |
03 | 3.6192: Use a less expensive method of waste removal | $5,465 | - | - | - | - | - |
$5,465
-
lb
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,567 | $18,988 |
$1,597
36,342
kWh
|
$1,970
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $2,618 | $500 | - | - | - | - | - | - | - | $2,618 | |
06 | 2.7261: Install timers and/or thermostats | $2,328 | $400 | - | - |
$2,328
-
MMBtu
|
- | - | - | - | - | |
07 | 3.8142: Distill contaminated solvents for reuse | $1,418 | $4,850 | - | - | - |
$1,749
-
gal
|
$(-87.0)
-
lb
|
$(-154.0) | $(-90.0) | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,284 | $5,000 | - | - | - | - |
$1,284
-
lb
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $477 | $180 |
$210
4,689
kWh
|
$267
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $373 | $640 |
$165
3,810
kWh
|
$208
-
kW-mo/yr
|
- | - | - | - | - | - | |
11 | 2.2437: Recover waste heat from equipment | $360 | $800 | - | - |
$360
-
MMBtu
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $31,099 | $52,858 |
$4,425
100,820
kWh
|
$11,255
-
kW-mo/yr
|
$4,634
-
MMBtu
|
$1,749
-
gal
|
$6,662
-
lb
|
$(-154.0) | $(-90.0) | $2,618 | ||
TOTAL IMPLEMENTED | $19,323 | $26,508 |
$1,972
44,841
kWh
|
$2,445
-
kW-mo/yr
|
$8,157
-
MMBtu
|
- |
$6,749
-
lb
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs