ITAC Assessment: WI0337
ITAC logo
ITAC Assessment: WI0337
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Specialty Contract Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 252,319
ft2
Annual Production 14,000
pieces
Production Hrs. Annual 2,375
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,613 3,885,991
kWh
Electricity Demand $111,945 15,830
kW-mo/yr
Electricity Fees $32,776 -
Natural Gas $87,875 25,444
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $98,691 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,196

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 3.2123: Convert to high volume low pressure (hvlp) paint guns $68,050 $1,000 - - - - - - - $68,050
02 2.7261: Install timers and/or thermostats $11,924 $1,600 - - $11,924
-
MMBtu
- - - - -
03 4.445: Install equipment to move product $5,222 $5,700 $(-3.0)
(-293)
kWh
$(-25.0)
-
kW-mo/yr
- - - $5,250 - -
04 3.8142: Distill contaminated solvents for reuse $3,492 $6,000 - - - $3,120
-
gal
$(-717.0)
-
lb
$(-1,271.0) - $2,360
05 3.3131: Use evaporation to concentrate material $3,019 $10,000 - - $(-200.0)
-
MMBtu
$4,096
-
gal
- $(-877.0) - -
06 2.7314: Reduce ventilation air $2,871 $500 $536
19,637
kWh
- $2,335
-
MMBtu
- - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,551 - $803
29,601
kWh
$748
-
kW-mo/yr
- - - - - -
08 2.4222: Install adequate dryers on air lines to eliminate blowdown $990 $5,024 $486
17,878
kWh
$504
-
kW-mo/yr
- - - - - -
09 2.4221: Install compressor air intakes in coolest locations $433 $640 $224
8,206
kWh
$209
-
kW-mo/yr
- - - - - -
10 2.8112: Combine utility meters $562 $200 - - - - - - $562 -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $400 $809 $213
7,913
kWh
$187
-
kW-mo/yr
- - - - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $177 $170 $97
3,517
kWh
$80
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $98,691 $31,643 $2,356
86,459
kWh
$1,703
-
kW-mo/yr
$14,059
-
MMBtu
$7,216
-
gal
$(-717.0)
-
lb
$3,102 $562 $70,410
TOTAL IMPLEMENTED $8,196 $11,364 $1,510
55,392
kWh
$1,436
-
kW-mo/yr
- - - $5,250 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs