Assessment Year | 1999 |
---|---|
Principal Product | Specialty Contract Furniture |
NAICS |
n/a
|
SIC | 2521: Wood Office Furniture |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
252,319
ft2
|
Annual Production | 14,000
pieces
|
Production Hrs. Annual | 2,375
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,613 | 3,885,991 |
kWh
|
$0.026 |
Electricity Demand | $111,945 | 15,830 |
kW-mo/yr
|
$7.07 |
Electricity Fees | $32,776 | - |
|
- |
Natural Gas | $87,875 | 25,444 |
MMBtu
|
$3.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $98,691 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,196 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $68,050 | $1,000 | - | - | - | - | - | - | - | $68,050 | |
02 | 2.7261: Install timers and/or thermostats | $11,924 | $1,600 | - | - |
$11,924
-
MMBtu
|
- | - | - | - | - | |
03 | 4.445: Install equipment to move product | $5,222 | $5,700 |
$(-3.0)
(-293)
kWh
|
$(-25.0)
-
kW-mo/yr
|
- | - | - | $5,250 | - | - | |
04 | 3.8142: Distill contaminated solvents for reuse | $3,492 | $6,000 | - | - | - |
$3,120
-
gal
|
$(-717.0)
-
lb
|
$(-1,271.0) | - | $2,360 | |
05 | 3.3131: Use evaporation to concentrate material | $3,019 | $10,000 | - | - |
$(-200.0)
-
MMBtu
|
$4,096
-
gal
|
- | $(-877.0) | - | - | |
06 | 2.7314: Reduce ventilation air | $2,871 | $500 |
$536
19,637
kWh
|
- |
$2,335
-
MMBtu
|
- | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,551 | - |
$803
29,601
kWh
|
$748
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $990 | $5,024 |
$486
17,878
kWh
|
$504
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $433 | $640 |
$224
8,206
kWh
|
$209
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.8112: Combine utility meters | $562 | $200 | - | - | - | - | - | - | $562 | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $400 | $809 |
$213
7,913
kWh
|
$187
-
kW-mo/yr
|
- | - | - | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $177 | $170 |
$97
3,517
kWh
|
$80
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $98,691 | $31,643 |
$2,356
86,459
kWh
|
$1,703
-
kW-mo/yr
|
$14,059
-
MMBtu
|
$7,216
-
gal
|
$(-717.0)
-
lb
|
$3,102 | $562 | $70,410 | ||
TOTAL IMPLEMENTED | $8,196 | $11,364 |
$1,510
55,392
kWh
|
$1,436
-
kW-mo/yr
|
- | - | - | $5,250 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs