| Assessment Year | 1998 |
|---|---|
| Principal Product | Napkins and Place Mats |
| NAICS |
n/a
|
| SIC | 2676: Sanitary Paper Products |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
120,000
ft2
|
| Annual Production | 2,400,000,000
pieces
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $121,256 | 3,477,140 |
kWh
|
$0.035 |
| Electricity Demand | $25,108 | 5,061 |
kW-mo/yr
|
$4.96 |
| Electricity Fees | $4,703 | - |
|
- |
| Natural Gas | $32,000 | 5,817 |
MMBtu
|
$5.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,186 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $54,000 | $20,000 | - | - | - | $54,000 | - | |
| 02 | 3.7137: Replace cloth rags with paper towels | $7,600 | - | - | - | - | - | $7,600 | |
| 03 | 2.7261: Install timers and/or thermostats | $5,103 | $1,400 | - | - |
$5,103
-
MMBtu
|
- | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,015 | $8,000 |
$(-388.0)
(-11,430)
kWh
|
- |
$4,403
-
MMBtu
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $4,802 | $7,200 |
$3,029
90,270
kWh
|
$1,773
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $468 | $640 |
$364
9,965
kWh
|
$104
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $75,988 | $37,240 |
$3,005
88,805
kWh
|
$1,877
-
kW-mo/yr
|
$9,506
-
MMBtu
|
$54,000 | $7,600 | ||
| TOTAL IMPLEMENTED | $17,186 | $10,040 |
$(-24.0)
(-1,465)
kWh
|
$104
-
kW-mo/yr
|
$9,506
-
MMBtu
|
- | $7,600 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs