ITAC Assessment: WI0251
ITAC logo
ITAC Assessment: WI0251
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Springs, wire forms
NAICS
n/a
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 300,000
ft2
Annual Production 168,000,000
lb
Production Hrs. Annual 5,250
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,019 4,665,006
kWh
Natural Gas $92,119 25,940
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,459

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,879 $9,720 $14,879
233,587
kWh
- -
02 2.7135: Install occupancy sensors $601 $375 $601
9,379
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,548 - $1,548
24,326
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $552 $1,500 $552
8,499
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $1,416 $1,280 $1,416
21,981
kWh
- -
06 2.7447: Install vinyl strip / high speed / air curtain doors $719 $656 - $719
-
MMBtu
-
07 2.2511: Insulate bare equipment $126 $525 - $126
-
MMBtu
-
08 2.2692: Use outside cold water source as a supply of cooling water $2,740 $6,000 - - $2,740
-
Tgal
TOTAL RECOMMENDED $22,581 $20,056 $18,996
297,772
kWh
$845
-
MMBtu
$2,740
-
Tgal
TOTAL IMPLEMENTED $3,459 $6,656 - $719
-
MMBtu
$2,740
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs