| Assessment Year | 1995 |
|---|---|
| Principal Product | Pneumatic Cylinders |
| NAICS |
n/a
|
| SIC | 3593: Fluid Power Cylinders and Actuators |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
75,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 5,600
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $73,694 | 1,158,558 |
kWh
|
$0.064 |
| Natural Gas | $9,609 | 2,562 |
MMBtu
|
$3.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,634 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $3,240 | $800 | - |
$3,240
-
MMBtu
|
- | |
| 02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,647 | $7,000 | - | - | $2,647 | |
| 03 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $2,170 | $1,000 |
$2,170
33,998
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $779 | $640 |
$779
12,309
kWh
|
- | - | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $656 | $2,000 |
$656
10,258
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $539 | $2,160 |
$539
8,499
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $157 | $514 |
$157
2,345
kWh
|
- | - | |
| 08 | 2.3132: Recharge batteries on during off-peak demand periods | $488 | - |
$488
-
kWh
|
- | - | |
| 09 | 2.6218: Turn off equipment when not in use | $276 | - |
$276
4,396
kWh
|
- | - | |
| TOTAL RECOMMENDED | $10,952 | $14,114 |
$5,065
71,805
kWh
|
$3,240
-
MMBtu
|
$2,647 | ||
| TOTAL IMPLEMENTED | $9,634 | $11,314 |
$3,747
50,997
kWh
|
$3,240
-
MMBtu
|
$2,647 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs