| Assessment Year | 1995 |
|---|---|
| Principal Product | Packaging of Cheese |
| NAICS |
n/a
|
| SIC | 2022: Natural, Processed, and Imitation Cheese |
| Sales Range | $10 M to 50M |
| # of Employees | 210 |
| Plant Area |
32,000
ft2
|
| Annual Production | 52,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $87,509 | 1,870,750 |
kWh
|
$0.047 |
| Natural Gas | $22,552 | 6,381 |
MMBtu
|
$3.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,915 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,262 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $4,423 | - | - | - | $4,423 | |
| 02 | 2.3137: Use power during off-peak periods | $2,146 | $1,000 |
$2,146
-
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $931 | $1,443 |
$931
19,930
kWh
|
- | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $888 | $2,000 |
$888
-
kWh
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $844 | $2,000 | - |
$844
-
MMBtu
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $683 | $640 |
$683
14,654
kWh
|
- | - | |
| 07 | 2.3132: Recharge batteries on during off-peak demand periods | $648 | $2,000 |
$648
-
kWh
|
- | - | |
| 08 | 2.7261: Install timers and/or thermostats | $203 | $200 | - |
$203
-
MMBtu
|
- | |
| 09 | 2.2437: Recover waste heat from equipment | $149 | $500 | - |
$149
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $10,915 | $9,783 |
$5,296
34,584
kWh
|
$1,196
-
MMBtu
|
$4,423 | ||
| TOTAL IMPLEMENTED | $2,262 | $4,083 |
$2,262
34,584
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs