ITAC Assessment: WI0210
ITAC logo
ITAC Assessment: WI0210
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Remanufactured starters and alternators
NAICS
n/a
SIC 3694: Electrical Equipment for Internal Combustion Engines
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area 48,000
ft2
Annual Production 276,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,280 686,987
kWh
Natural Gas $31,088 6,224
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,818 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,178

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7221: Lower temperature during the winter season and vice-versa $5,868 $1,400 - $5,868
-
MMBtu
-
02 2.8113: Purchase gas directly from a contract gas supplier $5,575 $500 - - $5,575
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,328 $5,154 $3,328
27,843
kWh
- -
04 2.7135: Install occupancy sensors $625 $375 $625
5,275
kWh
- -
05 2.2437: Recover waste heat from equipment $1,471 $2,200 - $1,471
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $1,288 $1,920 $1,288
10,844
kWh
- -
07 2.7447: Install vinyl strip / high speed / air curtain doors $551 $500 - $551
-
MMBtu
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $112 - $112
879
kWh
- -
TOTAL RECOMMENDED $18,818 $12,049 $5,353
44,841
kWh
$7,890
-
MMBtu
$5,575
TOTAL IMPLEMENTED $9,178 $6,020 $1,288
10,844
kWh
$7,890
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs