Assessment Year | 2018 |
---|---|
Principal Product | Wood Veneer |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
241,500
ft2
|
Annual Production | 16,000
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $145,522 | 3,045,200 |
kWh
|
$0.048 |
Electricity Demand | $77,894 | 8,943 |
kW-mo/yr
|
$8.71 |
Wood | $1 | 20,000 |
MMBtu
|
$0.000 |
TOTAL YEARLY COSTS | $223,417 | |||
RECOMMENDED SAVINGS* | $44,179 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,192 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,309 | $135,942 |
$14,300
299,166
kWh
|
$8,770
-
kW-mo/yr
|
- | $2,239 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,172 | $200 |
$1,364
28,539
kWh
|
$608
-
kW-mo/yr
|
$(-400.0) | $(-400.0) | |
03 | 2.4239: Eliminate or reduce compressed air usage | $1,006 | $1,350 |
$1,006
21,052
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $981 | $100 |
$671
14,046
kWh
|
$310
-
kW-mo/yr
|
- | - | |
05 | 2.4323: Use optimum size and capacity equipment | $4,293 | $10,000 |
$3,436
71,885
kWh
|
$857
-
kW-mo/yr
|
- | - | |
06 | 2.4323: Use optimum size and capacity equipment | $9,484 | $10,000 |
$7,592
158,819
kWh
|
$1,892
-
kW-mo/yr
|
- | - | |
07 | 2.4151: Develop a repair/replace policy | $1,934 | $5,865 |
$1,251
26,171
kWh
|
$683
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $44,179 | $163,457 |
$29,620
619,678
kWh
|
$13,120
-
kW-mo/yr
|
$(-400.0) | $1,839 | ||
TOTAL IMPLEMENTED | $42,192 | $162,007 |
$27,943
584,580
kWh
|
$12,810
-
kW-mo/yr
|
$(-400.0) | $1,839 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs