ITAC Assessment: WI0200
ITAC logo
ITAC Assessment: WI0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Stainless steel
NAICS
n/a
SIC 3556: Food Products Machinery
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 60,000
ft2
Annual Production 0
units
Production Hrs. Annual 5,600
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,830 755,569
kWh
Natural Gas $20,762 4,233
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,832 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $9,116 $500 n/a - - $9,116
02 2.7224: Reduce space conditioning during non-working hours $2,899 $800 n/a - $2,899
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,708 - n/a $2,708
45,721
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $303 $740 n/a $303
4,982
kWh
- -
05 2.7243: Improve air circulation with destratification fans / other methods $1,293 $3,675 n/a - $1,293
-
MMBtu
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,153 $1,000 n/a - $1,153
-
MMBtu
-
07 2.7135: Install occupancy sensors $360 $450 n/a $360
6,155
kWh
- -
TOTAL RECOMMENDED $17,832 $7,165 $3,371
56,858
kWh
$5,345
-
MMBtu
$9,116
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs