| Assessment Year | 1992 |
|---|---|
| Principal Product | ELEVATOR COMPONENTS |
| NAICS |
n/a
|
| SIC | 3534: Elevators and Moving Stairways |
| Sales Range | $10 M to 50M |
| # of Employees | 185 |
| Plant Area |
n/a
|
| Annual Production | 30,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $132,653 | 1,488,863 |
kWh
|
$0.089 |
| Natural Gas | $2,656 | 540 |
MMBtu
|
$4.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,814 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,517 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,114 | - |
$3,457
38,687
kWh
|
- | $(-343.0) | |
| 02 | 2.6232: Install set-back timers | $1,250 | $1,200 |
$1,250
14,068
kWh
|
- | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,806 | - |
$4,458
-
kWh
|
- | $(-2,652.0) | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $914 | $1,920 |
$914
10,258
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $603 | $128 |
$603
6,741
kWh
|
- | - | |
| 06 | 2.6214: Shut off pilots in standby equipment | $127 | - | - |
$127
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $7,814 | $3,248 |
$10,682
69,754
kWh
|
$127
-
MMBtu
|
$(-2,995.0) | ||
| TOTAL IMPLEMENTED | $1,517 | $2,048 |
$1,517
16,999
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs