Assessment Year | 1992 |
---|---|
Principal Product | MILK AND PLASTIC BOTTLES |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 66 |
Plant Area |
n/a
|
Annual Production | 104,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $218,820 | 5,026,084 |
kWh
|
$0.044 |
Natural Gas | $42,665 | 15,077 |
MMBtu
|
$2.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,929 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,046 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,410 | $3,576 |
$4,410
101,407
kWh
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,046 | $500 | - |
$3,046
-
MMBtu
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,080 | $960 |
$1,080
24,912
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $994 | $1,200 | - |
$994
-
MMBtu
|
- | |
05 | 2.7226: Use computer programs to optimize hvac performance | $463 | $1,400 |
$463
10,551
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $541 | - |
$591
13,482
kWh
|
- | $(-50.0) | |
07 | 2.7261: Install timers and/or thermostats | $268 | $600 | - |
$268
-
MMBtu
|
- | |
08 | 2.3132: Recharge batteries on during off-peak demand periods | $127 | - |
$127
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $10,929 | $8,236 |
$6,671
150,352
kWh
|
$4,308
-
MMBtu
|
$(-50.0) | ||
TOTAL IMPLEMENTED | $3,046 | $500 | - |
$3,046
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs