Assessment Year | 1992 |
---|---|
Principal Product | FRYERS,BREADINGS |
NAICS |
n/a
|
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 57 |
Plant Area |
n/a
|
Annual Production | 78,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,850 | 523,740 |
kWh
|
$0.070 |
Natural Gas | $8,091 | 1,892 |
MMBtu
|
$4.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,480 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,717 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $1,451 | - |
$1,382
-
kWh
|
$69
-
MMBtu
|
- | |
02 | 2.3191: Use demand controller or load shedder | $1,308 | $10,000 |
$1,308
-
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $874 | $2 |
$908
12,896
kWh
|
- | $(-34.0) | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $622 | $1 |
$841
12,016
kWh
|
$(-219.0)
-
MMBtu
|
- | |
05 | 2.6121: Reduce hot water temperature to the minimum required | $184 | - |
$184
2,638
kWh
|
- | - | |
06 | 2.1123: Install automatic stack damper | $452 | $500 | - |
$452
-
MMBtu
|
- | |
07 | 2.6214: Shut off pilots in standby equipment | $136 | - | - |
$136
-
MMBtu
|
- | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $205 | $150 | - |
$205
-
MMBtu
|
- | |
09 | 2.4221: Install compressor air intakes in coolest locations | $142 | $640 |
$142
2,052
kWh
|
- | - | |
10 | 2.3132: Recharge batteries on during off-peak demand periods | $106 | $150 |
$106
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $5,480 | $11,443 |
$4,871
29,602
kWh
|
$643
-
MMBtu
|
$(-34.0) | ||
TOTAL IMPLEMENTED | $4,717 | $10,643 |
$4,765
29,602
kWh
|
$(-14.0)
-
MMBtu
|
$(-34.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs