| Assessment Year | 1992 |
|---|---|
| Principal Product | AUTOMOBILE DIE CAST PARTS |
| NAICS |
n/a
|
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $303,443 | 6,484,467 |
kWh
|
$0.047 |
| Natural Gas | $210,962 | 60,869 |
MMBtu
|
$3.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $35,687 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,209 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $19,612 | - |
$11,911
-
kWh
|
$7,701
-
MMBtu
|
- | |
| 02 | 2.2443: Re-use or recycle hot or cold process exhaust air | $7,027 | $15,000 | - |
$7,027
-
MMBtu
|
- | |
| 03 | 2.3212: Optimize plant power factor | $5,209 | $9,758 |
$5,209
-
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,569 | - |
$2,121
41,618
kWh
|
- | $(-552.0) | |
| 05 | 2.6232: Install set-back timers | $179 | $200 |
$179
4,103
kWh
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,096 | $2,296 |
$1,096
24,326
kWh
|
- | - | |
| 07 | 2.2511: Insulate bare equipment | $327 | $312 | - |
$327
-
MMBtu
|
- | |
| 08 | 2.7224: Reduce space conditioning during non-working hours | $286 | - | - |
$286
-
MMBtu
|
- | |
| 09 | 2.7261: Install timers and/or thermostats | $271 | $600 | - |
$271
-
MMBtu
|
- | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $111 | $250 |
$111
2,345
kWh
|
- | - | |
| TOTAL RECOMMENDED | $35,687 | $28,416 |
$20,627
72,392
kWh
|
$15,612
-
MMBtu
|
$(-552.0) | ||
| TOTAL IMPLEMENTED | $5,209 | $9,758 |
$5,209
-
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs