| Assessment Year | 1990 |
|---|---|
| Principal Product | CUSTOM LOOSELEAF BINDERS |
| NAICS |
n/a
|
| SIC | 2782: Blankbooks, Looseleaf Binders and Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
n/a
|
| Annual Production | 4,500,000
pieces
|
| Production Hrs. Annual | 4,550
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $113,093 | 1,525,791 |
kWh
|
$0.074 |
| Natural Gas | $53,220 | 10,111 |
MMBtu
|
$5.26 |
| Fuel Oil #2 | $12,804 | 3,354 |
MMBtu
|
$3.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,716 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,686 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $26,686 | $500 | - |
$26,686
-
MMBtu
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $8,462 | $2,500 |
$9,750
57,151
kWh
|
$(-1,288.0)
-
MMBtu
|
- | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $7,033 | - | - |
$7,033
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $923 | $1,607 |
$923
12,603
kWh
|
- | - | |
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $2,409 | $4,908 | - | - |
$2,409
-
MMBtu
|
|
| 06 | 2.2533: Replace air curtain doors with solid doors | $1,655 | $2,000 | - |
$1,655
-
MMBtu
|
- | |
| 07 | 2.6232: Install set-back timers | $338 | $200 |
$338
4,689
kWh
|
- | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $210 | $1,000 |
$210
2,931
kWh
|
- | - | |
| TOTAL RECOMMENDED | $47,716 | $12,715 |
$11,221
77,374
kWh
|
$34,086
-
MMBtu
|
$2,409
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $26,686 | $500 | - |
$26,686
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs