| Assessment Year | 1990 |
|---|---|
| Principal Product | HYDRAULIC FLUID PUMPS |
| NAICS |
n/a
|
| SIC | 3594: Fluid Power Pumps and Motors |
| Sales Range | $10 M to 50M |
| # of Employees | 270 |
| Plant Area |
n/a
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $207,956 | 4,074,443 |
kWh
|
$0.051 |
| Natural Gas | $58,926 | 22,363 |
MMBtu
|
$2.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3135: Schedule routine maintenance during non-operating periods | $19,921 | - |
$19,921
-
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,064 | $12,726 |
$7,064
138,335
kWh
|
- | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,784 | - |
$2,784
-
kWh
|
- | |
| 04 | 2.6232: Install set-back timers | $1,952 | $1,000 |
$1,952
38,394
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,725 | $3,750 |
$1,725
33,705
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,725 | - |
$1,725
33,705
kWh
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $1,709 | $500 | - |
$1,709
-
MMBtu
|
|
| 08 | 2.2437: Recover waste heat from equipment | $1,107 | $1,000 | - |
$1,107
-
MMBtu
|
|
| 09 | 2.7494: Install storm windows and doors | $482 | $1,440 | - |
$482
-
MMBtu
|
|
| TOTAL RECOMMENDED | $38,469 | $20,416 |
$35,171
244,139
kWh
|
$3,298
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs